Current Construction / Road Closures

Town of Malta Complete Street Project Update



April 17, 2020
Mobilization began the week of April 13 and construction work zone signage was installed.
Construction of the Blacksmith Square sidewalk portion of the project is anticipated to begin April 20th.

Town of Malta
Complete Street Project
Update June 5, 2020
Construction of the Blacksmith Square Sidewalk is 95% Complete
Work on the Gateway Signage Commenced June 1st
Saw Cutting of Pavement Along Route 9 Expected to Begin June 8th (To begin heading north from Stonebreak,
 then circle back to the west side of Route 9 heading south)Installation of Drainage Catch Basins Expected to Begin June 15th (from south to north)

Town of Malta
Complete Street Project Update
June 24, 2020
Construction of the Blacksmith Square Sidewalk is 95% Complete
Work on the Gateway Signage Commenced June 1st
Saw Cutting of Pavement Along Route 9 Substantially Completed
Installation of Drainage Catch Basins Expected to Continue on East Side of Route 9 (from south to north) Before Beginning on West Side of Route 9
Installation of Curbing Expected to Start June 25th (from south to north) on East Side of Route 9

Project 25% Complete

Town of Malta
Complete Street Project Update

July 7, 2020
Construction of the Blacksmith Square Sidewalk is 95% Complete
Work on the Gateway Signage In Process

Installation of Drainage Catch Basins Expected to Continue and Be Completed on East Side of Route 9 (from south to north) Before Beginning on West Side of Route 9
Installation of Curbing in Process (from south to north) on East Side of Route 9
Installation of Sidewalk in Process (from south to north) on East Side of Route 9
Work Expected to Begin on West Side of Route 9 in Two Weeks

Project 35% Complete

Country Knolls Road Work

Sections of culvert piping and catch basins are being replaced in the Country Knolls area.
This will be done over a number of years.  The roads will be open for traffic during the work most of the time, there may be occasion for some very short closures.

LUTHER FOREST Road work


Another project that we have finally finalized planning for is the Luther Forest Catch Basins drainage.
We will be doing sections at a time each year replacing/widening drainage areas.
Kubricky Consruction will be doing the major part of the work with the Highway Department
These roads may need to be shut down for very short periods of time.

 Thank you for your patience during this work.